# Databases (https://docs.pulsarml.com/guides/desktop-app/databases)

Review and correct your machines' stop, production, operator and defect records, shift by shift, in Databases.



**Databases**, in the left-hand menu, holds your plant's records in four tabs: **Stops**, **Production**, **Operators** and **Defects**. Each lists one row per stop or per machine and shift, for the period and machines you choose, and lets you correct what was recorded: the quantity produced, the SKU, the operator on a shift, the defects.

## Choose the period and the machines [#choose-the-period-and-the-machines]

These two selectors, at the top right, are the same on every tab:

* **The date range.** Click it and pick the start and end dates on the calendar, up to 15 days. Under **Shift**, untick any shifts you don't want to see, then click **Apply**.
* **Machines** chooses which machines are listed.

Each tab's table shows records still in progress with **Live*&#x2A; as their end time, and a shift that ends the next day with &#x2A;*(+1)**. Click a column heading to sort by it. **Download** downloads the records listed.

## Stops [#stops]

The **Stops** tab lists every stop, where you classify, split and filter them. It has its own guide: [Stops](/guides/desktop-app/stops).

## Production [#production]

The **Production** tab lists what each machine produced in each shift: **Machine**, **Date**, **Shift**, **Start Time**, **End Time**, **Operator**, **Quantity**, **SKU**, **Nominal speed p/h**, **Production Order** and **Type**, followed by any custom fields you've added and **Actions**. The chip icon next to a machine's name means its production is counted automatically: hover over it to see "This advancement is automatized."

<Screenshot id="databases-production" alt="Databases on the Production tab. At the top, the Stops, Production, Operators and Defects tabs, the date range with its shift icons and Machines 14. Below, the SKU and Operator filters and Reset Filters on the left, and Import, Add custom field, Download and a gear button on the right. The table shows Machine (with a chip icon after each name), Date, Shift, Start Time, End Time, Operator and Actions, with a pencil and a split icon on every row, and a red trash icon on rows whose shift has ended; rows of the current shift show Live as their end time." width="1440" height="900" />

Narrow the list with the **SKU** and **Operator** filters: tick the values you want and click **Apply**. **Reset Filters** clears them.

### Edit a production record [#edit-a-production-record]

<Steps>
  <Step>
    Click the pencil in the row's **Actions**. The row becomes editable: **Quantity**, **SKU**, **Nominal speed p/h**, **Production Order** and your custom fields.
  </Step>

  <Step>
    Change the values, then click the check mark to save, or the **X** to discard the changes.
  </Step>
</Steps>

The red trash icon deletes a record. It only appears once the shift has ended.

### Split a production record [#split-a-production-record]

When a machine produced more than one SKU in a shift, split the record so each part has its own SKU and quantity.

<Steps>
  <Step>
    Click the split icon in the row's **Actions**. The **Split advancement** dialog shows the record's **Start Time** and **End Time**.
  </Step>

  <Step>
    Click &#x2A;*+** to add a time where the record splits, once for each split. **Next** becomes available.
  </Step>

  <Step>
    Click **Next**. Each part (**First production batch**, **Second production batch**…) shows its times. Open each one and fill in its **SKU**, **Nominal speed p/h** and **Product quantity**. Under the quantity, **Original sensor value** shows what the sensor counted.
  </Step>

  <Step>
    Click **Confirm**, or **Back** to change the times.
  </Step>
</Steps>

### Import production [#import-production]

Click **Import** to open **Upload your files**. Download the **sample file** to see the format, then drag your file onto the **Production** box or click **choose a file**, and click **Finish**. **Back to Production** returns to the table.

### Add a custom field [#add-a-custom-field]

Click **Add custom field**. In **Create a new custom field**, enter the **Field name** and choose its type: **Text**, **Text area**, **Number**, **Checkbox**, **Single select**, **Multi select**, **Date**, **Image** or **File**. Click **Apply** to add it, or **Cancel**. The field becomes a column on the **Production** and **Defects** tabs.

The gear button opens [Settings → Production](/guides/settings/production), where you manage SKUs, nominal speeds and defect categories.

## Operators [#operators]

The **Operators** tab lists which operator worked each machine's shift: **Machine**, **Date**, **Shift**, **Start Time**, **End Time**, **Operator** and **Action**.

<Screenshot id="databases-operators" alt="Databases on the Operators tab, with the Operator and Assignment filters on the left and Download and a gear button on the right. The table shows Machine, Date, Shift, Start Time, End Time and Operator, where each row's operator is a drop-down; the first row's drop-down is open, listing the plant's operators. At the bottom, 1 : 50 of 62 operator assignments and the page arrows." width="1440" height="900" />

* **Change the operator of a shift**: open the drop-down in the row's **Operator** column and choose another operator. This changes that shift only, not your [operator planning](/guides/settings/operator-planning#change-an-assignment-for-one-shift).
* **Split a shift between operators**: click the split icon in **Action**. In **Split*&#x2A;, click &#x2A;*+** to add the time when the operator changed, then **Next**.
* **Filter**: **Operator** shows only the operators you tick; **Assignment** shows **Assigned** or **Unassigned** shifts, with **Hide all** and **Show all**.

The gear button opens [Settings → Operators](/guides/settings/operators).

## Defects [#defects]

The **Defects** tab lists the defects recorded on each machine and shift: **Machine**, **Date**, **Shift**, **Start Time**, **End Time**, **Quantity**, **SKU**, **Category**, your custom fields and **Actions**. Narrow it with the **Production Order** and **SKU** filters; **Reset Filters** clears them.

<Screenshot id="databases-defects" alt="Databases on the Defects tab, with the Production Order and SKU filters and Reset Filters on the left and Download and a gear button on the right. The table shows Machine, Date, Shift, Start Time, End Time, Quantity and Actions, with a pencil on each row, and 1 : 10 defects at the bottom." width="1440" height="900" />

To correct a record, click the pencil in **Actions**. **Quantity**, **SKU**, **Category** and your custom fields become editable; click the check mark to save, or the **X** to discard.

The gear button opens the **Defects** tab of [Settings → Production](/guides/settings/production), where you manage the defect categories.